How to configure a start time for resources

In the My resources page (or another page name, depending on the default terminology defined or applied in the My activity page) configure the Work time / Automatic start time / Daily work time constraints.

Example 1: force a start time for resources

My resources start work at 8.00am, and finish at the latest at 6.00pm. The working time window is fully respected

Example 2: I would like TourSolver to suggest a start and finish time adapted to a defined first visit time

My resources can start from 8.00am onwards, and the finish time will be set accordingly. If the first visit starts at 10.00 and is located 10 minutes away from the start point, the resource will leave at 9.50m, and will be able to finish at the latest at 7.50pm (1 hour and 50 minutes later than the stated working day finish time). 

Example 3: I would like TourSolver to suggest a start time that respects the working day 

My resources can start from 8.00am onwards and finish at the latest at 6.00pm with a maximum working day of 8 hours